Arbor Energy just secured a $1 billion order to bring rocket turbine technology to the power grid


Energy startup Arbor Energy said Wednesday it has sold up to 5 gigawatts of its modular turbines to GridMarket, a company that helps arrange power projects for data centers and industrial users.

“Everyone wants more power. They wanted it yesterday,” said Brad Hartwig, co-founder and CEO ArborTechCrunch said. “Time frames are compressing and the scale is expanding.”

Arbor’s Halcyon turbines are based on rocket turbomachinery, a high-performance engine technology originally developed for spaceflight, and its first commercial turbines will be 3D printed and capable of generating 25 megawatts each. A GridMarket order, if fully fulfilled, represents 200 units.

Neither company disclosed the exact price of the deal, although Hartwig said Arbor has seen “a willingness to pay upwards of $100 per megawatt hour.” A person familiar with the deal told TechCrunch that the total runs into the billions of dollars.

The startup plans to connect its first turbine to the grid in 2028 and increase production until 2030, at which point it hopes to deliver more than 100 turbines annually. The goal is to eventually produce enough to produce 10 gigawatts of new capacity each year, Hartwig said.

Arbor’s initial designs are for Halcyon She lives on a vegetarian diet The power plant will absorb organic materials such as crop residues and wood residues from farms and timber operations, which will be converted into syngas – a combustible gas mixture – and burned in the presence of pure oxygen. The result will be pure carbon dioxide2Which can be captured and stored underground.

Under this process, each Halcyon turbine will generate carbon-negative energy. The organic matter they consume would otherwise decompose, releasing methane and carbon dioxide into the atmosphere.

TechCrunch event

San Francisco, California
|
October 13-15, 2026

Since then, Arbor has modified Halcyon to Acceptance of natural gas Plus biomass, which actually makes them more of a carnivore. Otherwise the process remains the same, which means carbon dioxide2 What appears can still be isolated.

Since it uses natural gas, it will not be carbon negative in this configuration. In fact, as methane leaks from pipes and valves throughout the supply chain, Halcyon’s fossil fuel-powered turbines will still produce some greenhouse gas emissions while also fueling continued demand for natural gas. Hartwig said the company works with suppliers of low-leakage natural gas, and that it is “economically beneficial to sequester carbon dioxide.”2“.

“We see a long-term path to less than 10 grams of CO22 “This is much lower than conventional natural gas-fired power plants without carbon capture, which release about 400 grams of carbon dioxide,” Hartwig said.2 per kilowatt hour.

Arbor has not given up on its bioenergy projects, and the sale to GridMarket is not limited to one specific fuel. However, there are other announced deals based on biomass Much smaller Of those signed with GridMarket.

Like many energy startups, Arbor got a big boost from the data center boom. Traditional gas turbine makers have faltered, and given the volatility of these markets in the past, they have been reticent about increasing production significantly. They would face intense pressure to ramp up production quickly, even if they wanted to, Hartwig said.

“These supply chains are all pretty much bottlenecked by the blades and rotors of conventional turbines,” he said. “These are fairly inflexible supply chains, both in terms of how artisanal the method of production is – doing single-crystal, directionally stiffened turbine blades – and also the highly specialized labour, the workforce behind it,” he said. “If you were to stand in line for a turbine today, you would be waiting until 2032.”

Arbor is betting that its machine-made and 3D-printed parts will help it get to market faster. “People want power for the next few years and they want a lot of it,” Hartwig said.

Leave a Reply